A failing retaining wall along the Kenduskeag Stream near Hannibal Hamlin Mall is getting replaced for about $3.87 million — construction runs through fall 2027.
At a glance
- Total mentions
- 2
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Oct 14, 2026.
Impact analysis
$3.87 million, within the anticipated budget.
Visitors to Hannibal Hamlin Mall Park and property owners along the stream.
Mentions & discussions (2)
City Council (Regular) - Oct 14, 2026
A failing retaining wall along the Kenduskeag Stream near Hannibal Hamlin Mall is getting replaced for about $3.87 million — construction runs through fall 2027.
Finance Committee (Regular) - Oct 5, 2026
A wall along the Kenduskeag Stream by Hannibal Hamlin Mall Park is failing, with blocks dislodging. The city is moving toward a $3.87 million design-build rebuild funded by Downtown TIF money, with design starting this fall and construction through 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bangor
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.